Environmental monitoring of a project shows whether, and how, its construction and operation change the surrounding environment. That needs a baseline to compare against, which is built up over three phases. In Italian practice these are known as ante operam, corso d’opera and post operam.
The ministerial guidelines on monitoring plans for projects subject to EIA describe their roles: the pre-construction phase builds the baseline, while the construction and post-construction phases check the predicted impacts, how well mitigation works and any impacts that were not foreseen.
Before construction
This phase describes the state of the environment before work begins. Its measurements are the reference for everything that follows, so stations and methods should be defined in a way that can be repeated. According to the guidelines it can already start in the permitting stages that follow the EIA decision.
During construction
This covers the works themselves, when pressures on the environment change fastest, for example noise, dust or effects on water. Measurement frequencies are often higher. The guidelines include setting up the site, the works themselves, dismantling the site and restoring the area, with campaigns tied to the works schedule.
After construction
This covers the period after the works end, with the project in operation. It shows whether environmental components settle into a stable state that can be compared with the baseline. The guidelines include operation and any decommissioning of the project, with a length that depends on the type of project.
Why every record needs its phase
If the phase is not recorded on every survey, comparing before, during and after becomes manual work that is prone to error. Recording it at the point of entry makes filters and exports immediate.
The length and content of each phase depend on the approved monitoring plan and the requirements of the competent authorities. For projects subject to EIA, Italian Legislative Decree 152/2006 (article 25) requires the decision to set out the monitoring measures, with parameters and duration proportionate to the nature, location and size of the project and the significance of its effects.
Example with made-up data
Example: the phases of a road bypass
A made-up project, a road bypass, might have a pre-construction phase of 12 months before the site opens, a construction phase of 30 months with campaigns tied to the progress of the works, and a post-construction phase covering pre-operation and the first three years of operation.
The noise stations measured before construction are measured again in the later phases, so the comparison is made on the same points. The durations are illustrative only: the real ones are set by the approved plan and the environmental conditions of the decision.
Sources
- Linee Guida per la predisposizione del Progetto di Monitoraggio Ambientale (PMA) delle opere soggette a procedure di VIA – Indirizzi metodologici generali (Capitoli 1-2-3-4-5)(opens in a new tab)
Ministero dell’Ambiente (MATTM), ISPRA, MiBACT, Rev.1, 16/06/2014, section 4.3 (p. 12) and section 5.5, Table 2 “Fasi del Monitoraggio Ambientale” (p. 25); in Italian. - Linee Guida per la predisposizione del Progetto di Monitoraggio Ambientale (PMA) delle opere soggette a procedure di VIA – Indirizzi metodologici specifici: Atmosfera (Capitolo 6.1)(opens in a new tab)
Ministero dell’Ambiente (MATTM), ISPRA, MiBACT, Rev.1, 16/06/2014, section 6.1.1 (pp. 5-7); in Italian. - Decreto legislativo 3 aprile 2006, n. 152, Norme in materia ambientale, art. 25(opens in a new tab)
Normattiva, current text, paragraph 4, letter c; in Italian.